resource assignments

A
Ajeej N 👤 Member for 16 years 1 month

hai,

 

I have a recovery program and the activities have some actual start dates. The activity duration type assigned is fixed duration and units.

Resources assignments have - Preserve units, duration and units/times assigned.

but when i check the resource usage spread sheet, in updated activities,  the Actual units  + remaining units doesnt match to budgeted units. i have assigned resources as budgeted units.

Can anybody help me out

 

regards

ajeej 