please help me how to use lag.how to see it
problem in using lag
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Faheem
You will get a lot of contradictory advice but the best advice I can give you is use only FS links and only use lags to represent drying out or curing periods - set to Calendar Days
Any other form of lags is bad planning practice.
See the debate that I started on Ban These Planning Abominations.
Best regards
Mike Testro