Planned percentage and actual percentage for shutdown jobs

S
sunil k 👤 Member for 14 years 8 months

Dear all,

 

I am working in the planning department and i am required to make a planned and actaul percentage on a daily basis and required to draw the S curve for the same.The jobs invloved will be of different categories and is required to be completed in a dparticlular time span.How do i dwvolop the same.Is it better to use excel for the same.

 

Regards

Sunil.k

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts