Starting the work day 8.10

B
Bony John 👤 Member for 21 years 8 months

 

Hi All,

 

Is there any way in P6 we would be able to fix the start of the day at minute interval in work calendar ? for eg. 8.10 as the start time in the calendar..

 

Your help is appreciated.

 

Bony

R
Raymond Au-Yeung 👤 Member for 23 years 6 months

Dear Bony,

Do you mean you found awkward minutes as the start time in the column fields of Start Dates / Finish Dates instead of Calendar? Why I ask because according to the calendar setting, the minutes should be 00 or 30. The setting has only allowed the smallest unit of half hour increments / intevals. In normal circumstances, by default the minutes in the "Dates" should be displayed as 00 or 30 normally. However your situation might be happened under the following 1) you have manually plugged in one activity (probably the first activity or first milestone day) the start date with 8 h 10 min or 2) you have 2 or more calendar settings having different working hours. The solution is: you could debug the error by changing manually the start time to 00 (remember display the time also in the "Dates" columns) or close the project, hgihlight the project, and check the default time of Planned Start and Data Date whether they are set at 00.

Enjoy Primavering!
Raymond Au-Yeung

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts