Hi Guys

 

Any idea on how to import key activities/Milestones from a detailed Programme plan to a Consolidated master plan without manually retyping it.

I know you can import the whole plan and if there is a change it changes in the Mater. i dont want to have to import the whole plan just want to import specific activities into the master and track the updates from the master.

  