Improved Planned Completion Date - NEC

T
TONY SEWELL 👤 Member for 15 years 9 months

I have an issue at present whereby we have been working to a target programme for a while and have recently combined these dates with the Cl32 programme and therefore the P.C has come back by 11 weeks.

 

The programme went in for submission but has recently come back with a non accpetance, therefore the alast accepted programme has a P.C date +11 weeks compaired to this last submission (it is realistic to achieve this new completion date).

 

We have just receieved a PMI for additional works, if assessed under the last accpeted programme then the works can be accomodated to some extent and only cause a slight delay.

 

However if assessed under the new P.C date then it has a bigger impact. Therefore have i got a case to say that we feel we should assess under this new programme logic (-11 week P.C albeit programme is not accepted) or do I have to assess on accpeted programme logic.

 

The new P.C -11 week logic is quite different therefore the assessment on the accepted programme would be unrealistic. Or becuase the -11 weeks to P.C is not accpeted is PM within rights to use up available float still within the accpeted programme?

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts