Progress Percentage by using late dates

Dear Friends 

Suppose you have an activity A .

whose early dates are 

Early Start  1 Apr 11 

Early Finish  30 Apr11

Whose Late Dates area 

Late Start 25 April 11

Late Finish 10 May 11

Now we are at 1 may , as per ealry dates your  planned progress must be 100 % while the  activity is 90% complete. This shows that it is delayed , now we want to use float then how to calculate planned progress  ?  so as not to show that we are delayed 

Thankyou 

Umer Mehmood

 

G
Gary Whitehead 👤 Member for 17 years 2 months

Typically you would plot 3 progress curves: planned (early), planned (late) and actual/forecast.

This is often called a "banana graph"

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts