Changing OD w/out automatically changing activity % complete

Hi All,

Im making a revised schedule and this is one of my problem. I want to change the Original duration without changing automatically the Activity % complete. these activities already started and there are already progress on it.
I'll appreciate any help you give me. Thanks.

E
ECHEZONACHUKWU OBIEKWE 👤 Member for 15 years 10 months

Hi John,

 

It all depends on the kind of progress % complete type you are using, if it is duration % then it would be affected but if it is physical % complete then you can go ahead to input the correct original duration to reflect the obtainable duration. if you are using units %, it depends on the quantity of the job delivered for you to get the progress %.

I will advice you to always use physical % complete type so as to give accurate progress on the job.

Regards,

Eche.

M
Muthukumaru Senthuran 👤 Member for 15 years 1 month

Hi Jone;

 

Basically you are revising this duration due to inaccurate of the original planned duration, it means the started activity could not progress as you planned . Progress % and remaining durtion to be determined by you.

 

Senthuran

M
Mike Testro 👤 Member for 20 years 6 months

Hi John

If you cannot just extend the end date of the uncompleted section then you may have to take off the progress - extend the durations and then add back the progress.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts