High Level Planning Assignments

K
Ken Barrett 👤 Member for 19 years 1 month

I have a fully resourced schedule completed. I am looking to run a report on the WBS level that will include the WBS name, The Budget for the WBS element, and the planning resources for that WBS element. I can not figure out how you assign a high level planning resource to the actual wbs element so that I can print off a nice report that states who will be the responsible manager/planner and controller for each wbs element

Any Help would be great!!

 

Ken

J
Joao Ribeiro 👤 Member for 23 years 3 months

High Level resources just work in the Web version. You may achieve what you want by creating WBS type activities and assigne them the resources you want.

HTH

Joao

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts