i want to show activity which is occuring every month during project duration....e.g.monthly /biweekly meeting.(duration 1 day max. only)

i want to show it as a one activity only; in one bar with gaps between each occurence.

how can i show it in p6?

S
Shah. HB 👤 Member for 17 years 6 months

Hi

You can try using Activity codes,first identifying activities repeating on particular month assign proper activity code .On applying filter you might get the list of activities you need to show.

 

On summarizing the activities present in the above layout (After activity code assignment and filter ) ,you might get one single bar 

 

Regards

Shahul

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts