There are some dicrpency with my main contractor's planner
the case is,
i said to main contractor's planner that you can use a total float of an activity when the finish milestone is with Zero float. My main contractor's planner is having total float in activity as well as in finish milestone also. i told them to follow early start/finish dates, which will lead to early finish of finish mile stone and if you follow late start/finish considering the total float of an activity, it will lead to late finish of finishmile stone (which has float) . My contractor's planner said to me that he can use the total float and can delay the activity when the finish milestone with total float.
is main contractor's statment correct.? please clarify
Hi Karthikeyan
Assuming that float you mentioned in this subject is total float
Please check the below link ,
http://en.wikipedia.org/wiki/Float_(project_management)
Regards
Shahul
First decide whether your project has one finish date or two finish dates???