Deploying Earned Value to a programme with NO Resource cost (all projects delivered by contractors)

R
Ronny Don 👤 Member for 16 years 6 months

I would like any views or experiences of deploying Earned Value or what has been deployed to fill the EVM requirement on programmes where all projects are tendered as turnkey (goods & service) to single suppliers (external contractors).

I will submit complete analysis of findings back on to the site.

Thanks all in advance

Ronny

R
Ronny Don 👤 Member for 16 years 6 months

Daniel

Thanks for that. You say what my experience points to, just wondering if there was something I missed? Don't think getting true EVM is possible? and do I really need it, or benefit any more from it? can't see how.

Thanks again

 

Ronny

D
Daniel Limson 👤 Member for 24 years 8 months

Hi Ronny,

In the absence of cost data, you can based it on quantities with a weighted value or you can based it on Manhours or Mandays but it does not give you a complete EVM analysis.

Best regards,

Daniel

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts