I need some information on a Water Pipeline Project

Hi 

A Very Very Happy New Year to members of Planning Planet.

I am a young professional in Planning & have never work before either on site or on a Planning & Scheduling. My goal is to become a successful planner & I got opportunity in my current organization now. I am looking some guidance on this issue.

If any one has complete library of Manpower & machinery calculation please guide me on [email protected]

My project is not a big one but the items are included as follows.

1-Road Diversion

2-Relocation of existing Utilities

3-Excavation & formation preparation

4-Bedding of Material & Laying of Pipe

5-Welding of Pipe in Trench

6-Construction of Thrust Block

7-Initial Back Filling

8-Testing

9-Sterilization and cleaning

10-Final Back Filling

11-Restoration of Asphalt

Construction of Valve Chambers

1-Setting out

2-Excavation for Manhole

3-Blinding

4-Construction of Base

5-Construction of Wall

6-Installation of Fittings & Valve

7-Test

8-Cover Slab

I never worked on any pipeline project before, only worked on Railway & Highway project in Drawing & Quantity section. This project is in Saudi Arabia. I am on a junior level so I don't have information related to soil, or any other issue which may required to planning,

If you have specification of pipe line project & any design book for design of valve chamber please share with me.

Here I need manpower & machinery calculation, how much gap should be gap between each activity. I know MSP & P6 but not expert.

You can guide me on [email protected]

Farooque

+966-544943431

+91-9701062756

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts