Schedule Calculations

There are a range of options for the calculation of dates and float in a CPM network.

I’ve just finished a draft White Paper focusing on the basic calculations and would appreciate comments on the correctness of the calculations and the methodology adopted.  The aim is to produce a definitive document that is generally agreed. 

You can download the paper from http://www.mosaicprojects.com.au/PDF/Schedule_Calculations.pdf  All comments gratefully appreciated.

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Hi Patrick,

the paper is very useful for understanding CPM calculations.

Not everything is applicable to Spider Project - we use additional types of activities, links, and lags. Besides, we don't approve negative floats.

I think that you shall reconsider adding 1 to activity dates.

If an activitiy starts in the middle of th day it is not necessary. I would suggest to write that 24:00 of the previous day and 0:00 of the next day are the same. And set the rule that activity always finishes at 24:00 and starts at 0:00. With this rule the problem does not exist. Actually activity duration may be measured in seconds.

Best Regards,

Vladimir

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts