Dear all,
I would like to talk about a method I developed about Work Breakdown Structure: the 3D WBS.
The idea is that there are 3 dimensions by project phase.
- Engineering Task = Discipline x Functional Systems x Activity or (Discipline x SBS x ABS)
- Procurement Task = Localisation x Product x Activity or (GBS x PBS x ABS)
- Construction Task = Localisation x Product x Activity or (GBS x PBS x ABS)
- Commissioning Task = Discipline x Functional Systems x Activity or (Discipline x SBS x ABS)
There are 3D Cubes under each phase.
The list of tasks is obtained by matrix.
I think that all the projects have this standard WBS.
What do you think about this approach?
Regards,
Hi
Can u pls paste a snapshot of sample WBS on the same approach .
Regards
Vinay
Hi Jean-Yves,
Spider Project users can create any number of parallel WBS for the same project and switch between them on mouth-click.
We usually recommend to create at least three WBS - based on objects, processes, and responsibility. Other structures may be based on locations and other properties of specific project.
So your approach is supported.
Best Regards,
Vladimir
A task in a little cube inside the cube of the phase. It has properties in terms of Predecessors, duration, resource...
[[wysiwyg_imageupload:165:]]
Hi,
For example, this is the matrix for the Construction phase:
[[wysiwyg_imageupload:166:]]
After analysis of the all the correspondences, we obtain the list of task below:
[[wysiwyg_imageupload:167:]]
Finally, if we look at each phase, we have this WBS.
[[wysiwyg_imageupload:168:]]
Best regards,