Copying Only Resources to all activities

Hi i had prepared a schedule with out assigning any resource to a project.now i need to assign as per project requirement.so i find little difficult to add resource to all activities.

my Question is can we add resources in one go to all activities  and later we can change value if needed.sothing like that rather adding resource by clicking each activity and assigning.

hope you got the question 

my email id: [email protected]

K
Kannan CP 👤 Member for 17 years 11 months

Hi Waheed,

If you are using P6, then select the required activities in the schedule. After that right click the mouse and assign resource of your choice to the activities. It is the solution. In P3 go for a global change.

Kannan

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Waheed,

please specify the software that you use.

It is easy in Spider Project but I expect that you use something else.

Best Regards,

Vladimir

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts