Requirement for Level 1 Program

D
D Artagnan 👤 Member for 17 years 8 months

I just wanna ask you guys. I was given a task to review a Level 1 program from the contractor by my manager. It's my first time reviewing one. Aside from the required activities that should be there (on a summary level), s-curves (based on early and late dates), manpower and equipment requirements, etc), what else should the contractor submit? What else should I take into consideration when reviewing a Level 1 Schedule?

I hope someone can clarify this to me. Would appreciate it.

R
Rafael Davila 👤 Member for 22 years 3 months

Level (-2) All Owner Jobs (To the Owner "The mother of the Whole")

Level (-1) Owner Jobs by Municipality

Level 0 Individual Owner's Job

Level 1 All Contractor's Portfolios

Level 2 Individual Portfolios

Level 3 Jobs By Continents

Level 4 Jobs By Country

Level 5 Jobs by Municipalities

Level 6 .... whatever gets down your pants

Level 10 Whole Project

Level 11 Zones or Sections

Level 12 Workfront summaries under Level 2

Level 13 Task Cascades for each workfront

Level 12 Individual tasks

I see the pretentious of some to define a "Universal" self serving definition of levels quite stupid. It shall means different to many, depending on your needs.

I use several WBS definitions for a single job, each with different levels, this complicates the above myopic vision.

My needs do not fit within Mosaic Definitions nor others, more frequently than not does not fit the client needs. Let every one use his own, let Owners require whatever they feel fit, let Contractors use whatever they feel fit.

P.S. If negative float is not an erroneous concept I guess negative level is not.

L
Leo Pearson 👤 Member for 15 years 4 months

A powerful share, I just given this onto a colleague who was doing somewhat analysis on this. And he in actual fact bought me breakfast because I found it for him.. smile. So let me reword that: Thnx for the deal with! However yeah Thnkx for spending the time to debate this, I feel strongly about it and love studying extra on this topic. If doable, as you become expertise, would you thoughts updating your blog with extra details? It is extremely helpful for me. Big thumb up for this blog put up!
shooting games meningiomata helicopter game interrobang sudoku puzzles otorhinolaryngology

P
Puneet Gupta 👤 Member for 15 years 6 months

Hi Artagnan,

The purpose of this level 1 programme is to show the coordination of all aspects of the project like feasibility, design, procurement, manufacture, assembly, production,construction, installation and commissioning.



It is presented not only as a barchart, but also with a set of milestone dates against which the project is monitored.

Ideally, this programme should be no more than a single sheet, containing perhaps 30 to 100 activities (depending upon the complexity of the project).

This programme/schedule will normally illustrate the critical path of the project.

The important point here is to consider who will receive and review this level 1 programme/schedule, which can often include people who do not readily understand such matters, meaning that the level of complexity should reflect this.

Regards,

Puneet Gupta

Bau Management + Consulting GmbH

A
ashraf alawady 👤 Member for 19 years 9 months

Dear all,

level one will show the main gauid lines of the prepared program like but not limited to

The contractrual milestones ,WBS for the major ativities ,constrains,mangement milestos,ay other cotractual or techeical requirements.

upon the approval of the above the detailed program with recources loaded and cost loaded and cash flow ca be prepared ad submitted for approval.

P
promise nukah 👤 Member for 15 years 6 months

i need sample report of the following document-progress report procedure, project calender procedure, report register. Also need guide for the preparation of level 1 , level 2 and level 3 baseline schedule.

T
Tom Howard 👤 Member for 22 years 11 months

Ok, been planning for 10 years, and only in the last 12-18 months have I heard people referring to Level 1, Level 2 etc programmes. (Everyone is at it - even my mate who is a PQS and knows diddly jack about planning, but confidently drops it into conversation as if he has a PhD in "Level" planning)

5 years ago people (at least all the ones I dealt with in the industry) talked about Summary Programmes, Detailed Programmes etc

All of a sudden its "Levels" as if there is a universal meaning to the word. Did I miss an industry wide email introducing and explaining the term too?

Surely it's such a meaningless word as well, as it will mean completly different things depending on what you are planning

S
Sathiaraj kandasamy 👤 Member for 15 years 7 months

Hi....

My Dear Friends,

THis is SathiarajKandasamy from qatar.

i need one clarification in Primavera P6.

How to incorporate in Primavera for Actual % Completion(Progress) = Planned % Completion(Progress).

For Example i have already one approved execution programme for my project.

One Project Completion for Planned=100%, but Actual=45% only.

I want to submit revised or recovery execution programme.

So Anybody please help me.

Thanks & Regards,

Sathiaraj Kandasamy

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts