Vertical and Horizanta projects planning

R
Rola Sabbah 👤 Member for 16 years 6 months

Hi planning planet,

i have a question, what is the criterias taking into consideration while planning for horizantal and vertical projects?

for vertical projects such as towers, for example we consider that 60% of the project duration is for skeleton but for horizantal like factories less due to the presence of E/M fixes.

what other basic factors in planning do u professional planners do? i mean even before developing the project like setting out the major milestones in the project.

Thanks

M
Muhammad AQEEL 👤 Member for 15 years 8 months

URGENT!!!

Dear All,

I 'm facing a problem with clander like;

One i give duration One day e.g: activity start on 12/10/2010 and will be finish on 12/10/2010 than this will be consider one right duration  But with me on the schedule date is comning 13/10/2010 instead on 12/10/2010 and showing the org. Duration is 1 (one). Can some one fix this problem. this will be much appriciated.

Regards,

maqeel

([email protected])+966599981584

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts