Manhours for piping in trenches
Forum Sponsor
Top Posters
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
Hi-Rinus,
Piping inch dia based on Pipe sch./class , in gerenal we can assume 30- 40 inch Diameter weld per day by one welder, in case of pipeline projects for STD class pipe,
Pipe trench , execavation depands on soil capacity , we can assume 80 -100 mtr Q. for normal soil.
Back filling subject to how many equipment you want to use,
HTH
Hi Rinus
Welcome to Planning Planet.
What exactly is "Process Piping"
This is a very complex question and you seem to be excluding the main factors that determine productivity.
Just laying the pipes in the trench is a side issue compared with all the other factors of urban engineering.
I would be more concerned with traffic control - section lengths - underground obstructions etc.
Unless of course you are on a greenfield site.
Best regards
Mike Testro