EPC Deliverable

S
Shazia khan 👤 Member for 18 years 1 month
I
Imran Malik 👤 Member for 12 years 4 months

Dear All,

 

is there any project control audit template / check list available  for the EPC Engineering Audit , please share

S
Satish Kumar 👤 Member for 16 years 3 months

As far as Contracts are concerned they are not, in planning and programming they are, i do agree.

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Satish,



Milestone is a zero duration and zero resource activity.



With kind regards,



Samer

S
Satish Kumar 👤 Member for 16 years 3 months

Deliverables will usually be stated as milestones by the client; refer the milestone mentioned in your contract; further, if you require a subcontractor for a specialised work on which your work will depend then it will be a deliverable for the sub contractor;

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Shazia,



The deliverable of the project is the end product that the client will utilize.



During the coure of the project, you will have plenty of deliverables as Shahul stated. It depends on the Project Management System that is agreed between the two parties.



What are you trying to achieve by identifying the deliverables?



With kind regards,



Samer

S
Shah. HB 👤 Member for 17 years 6 months

Hi Khan



In Engineering ,production of workshop drawings is one of the deliverable



In procurement ,material arrival on site is one of the deliverable



In construction, completion of sectional milestone mentioned in condition of contract is one of the deliverable



In commissioning, available of wild air is one of the deliverable


Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts