Contractual Milestones

S
SAM SHAI 👤 Member for 15 years 10 months
S
SAM SHAI 👤 Member for 15 years 10 months

Thanks a lot guys I agree with you that the intermediate contractual Milestone dates must not have constraints to allow the logic to play freely and give us a good critical path.

R
R. Catalan 👤 Member for 20 years 9 months

Sam,



It is not advisable to put a constraint on intermediate milestone as explained by Gary.



But if you want to show negative variance at project completion date, I don’t see any problem to apply "must finish by" constraint on project completion milestone at project level.



Best regards,



R. Catalan

G
Gary Whitehead 👤 Member for 17 years 2 months

If you put a constraint on an intermediate contractual milestone which is logically linked to the programme, it will adversely affect the calculation of total float, and hence the critical path.

Many clients require this, in my view incorrectly.



My prefered method is to show a forecast date for each critical milestone (which is logically linked), and immediately below this, add an isolated milestone showing the contract date so any forecast slippage vs contract can be easily understood, without affecting the critical path.

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Hi,



If it is a Contractual Milestone, then you must include it because your program of works much reflect the scope and delivery time.



A milestone is a zero duration activity, you will need to put a "Must Finish By" in order to achieve the Contractual requirement. Otherwise, the milestone will move with the critical path depending on the progress.



With kind regards,



Samer

M
Mike Testro 👤 Member for 20 years 5 months

Hi Sam



The only restraint that has a valid purpose in programming is the Project Start Milestone.



All others affect the critical path and should not be used.



Best regards



Mike Testro

S
SAM SHAI 👤 Member for 15 years 10 months

Contractual Milestones are to be achieved by the contractor as any other deliverable.



So incase it is not constrained then it will move freely when the progress is updated and if it has no impact on the end date then it will also have float and hence the contractor will not target to achieve this intermediate milestone.



I believe it is a must to have contraints on the intermediate milestones. As these intermediate milestones will convert this into a subproject (literal terms) and the contractor must achieve this date.


G
Gary Whitehead 👤 Member for 17 years 2 months

Sam,



Do you constraint the date of any other deliverable?



If you do not allow the milestone to move freely, 3 things happen:

1) The schedule will not show when the milestone is forecast to be achieved

2) Any activities down stream of that milestone will not be correctly forecast

3) You will loose the ability to automatically calculate the critical path through the entire project



I do not believe it is true to say a contractor will not target to achieve an intermediate milestone just because it is not constrained to target date.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts