Exporting Only some Activities
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Kumar,
Filter those activities that you want to copy and do the copy and paste but make sure that both project are open (old & new) then organized (Group & Sort) by EPS/WBS.
Dera Sir,
since i have thousands of activities inside the wbs which i am copying,is there any method to copy only some jobs which are coming in that wbs.
i have gruoped the equipment with category wise.for ex pumps.
so i want all the pumps activities only to be copied to the new project.
any suggestions...
Hi Kumar
You can filter those activities to export and save it as layout wih WBS of desired name .Copy and paste to the palace where you need it to export
Kumar,
Create a new project then open both project (old and new) then use WBS window and drag & drop or use cut & paste from old to new.