Exporting Only some Activities

K
kumar s 👤 Member for 16 years 5 months
R
Rodel Marasigan 👤 Member for 19 years 8 months

Kumar,

Filter those activities that you want to copy and do the copy and paste but make sure that both project are open (old & new) then organized (Group & Sort) by EPS/WBS.

K
kumar s 👤 Member for 16 years 5 months

Dera Sir,

since i have thousands of activities inside the wbs which i am copying,is there any method to copy only some jobs which are coming in that wbs.

i have gruoped the equipment with category wise.for ex pumps.

so i want all the pumps activities only to be copied to the new project.

any suggestions...

S
Shah. HB 👤 Member for 17 years 7 months

Hi Kumar



You can filter those activities to export and save it as layout wih WBS of desired name .Copy and paste to the palace where you need it to export

R
Rodel Marasigan 👤 Member for 19 years 8 months

Kumar,

Create a new project then open both project (old and new) then use WBS window and drag & drop or use cut & paste from old to new.

Forum Sponsor

Top Posters

James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts