Man Months for a project
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Pinan,
It is very simple, computation on manpower requirements for construction in Royal Commissions project shall be multiplied by 26days/month and for camp accomodation computation shall be multiplied by 30days/month. Royal Commission provided a sample spreadheet for Manpower Tabulation (for construction) and separate table for Camp Accomodation to be filled up by the contractor. RC gives only man-month data and it is up to the contractor or bidder to comply with. Actually, it is man-days that the RC required and not man-hour.
i hope this is clear to you now. i know that Rizwan understood this because he has the ITB documents with him.
cheers,
Pinan T.,
man-month; man-hour; and man-day are units, in my understanding, it is one-unit-per-unit, quantity is another story
cheers
i still can’t get it
10,155 man-month should be equal to 406 men per day, right?
i am not sure, but if you mean 10,155 as man per day, isn’t it too much?
or man-month is average man per day per month?
Hi Pinan,
You are right, thats why i mentioned to Rizwan to multiply it only by 26 days for manpower tabulation and 30 days for camp accomodation tabulation.
Cheers,
Hi everyone, so man-month means man per day?
because you multiply by 30 or 25days per month
isnt it that man-month is the total manpower per month?
just getting some information
Hi Daniel & Rizwan,
Let us be specific, Rizwan is working for Royal Commissions Project. Ive have done so many tender projects already with RC and Rizwan confirmed to me from PM that he is doing a bridge project for RC. Royal Commission always giving man-months only and its up to the contractor to compute and tabulate the manpower to be used for construction and camp accomodation as well.
This is for your info and might help if someone has a tender project with Royal Commission.
Cheers,
Generally, you are correct in your calculation
What you should consider is your companys working hours per week and consider the number of holidays per year as well For example:
work week = 6 days per week + holidays (depending on Country) normally up to 12 days per year
Working Hours per day = 10 hours with 1 hour break for lunch
so effectively, base on the above example you are only working 9 hours per day at 25 days per month.
So 10,100 Man Months is equivalent to
10,100 x 25 x 9 = 2,272,500 manhours
Dear Rizwan,
As other members said, please ensure that you are using the right calendars and holidays, as per Clients requirements / suggestions mentioned in the ITB document.
Regards,
Rizwan,
in addition, multiply it by 30 if for camp accomodation purposes.
cheers,
Rizwan,
you have to check also your working calendar. if you will be using a 6-day calendar you have to multiply it by 26 only. are you working with royal commission project?
Rizwan you are right
For example:
Man hours 3000
Man days 3000/10 =300 ( 10hrs/day )
Man Months 300/30 =10 ( 30 days/month)
ManMonths Manhours
10 10*30*10=3000
my understanding is multiply by 10 hours/day only if you need in manhours