Effort driven vs resource driven

L
Lucas l 👤 Member for 16 years 2 months
S
Stephen Devaux 👤 Member for 21 years 2 months

The sensitivity of an activity’s duration to resource addition is called its "resource elasticity". It’s an important characteristic for a planner to now, but it’s not very easily handled in software.



In the Total Project Control process, it’s managed by getting a second duration estimate: the Doubled Resource Estimated Duration, or DRED. If an activity is estimated to take 20D with a given load of resources, how long would it take if the resources are doubled. Possibilities include 10D ("perfectly resource elastic"); 12D (more common than 10D in most non-construction activities); 16D; 20D ("not resource elastic at all"; or 30D (installing the avionics in the cockpit of a jet fighter). Such variations are the sort of thing that there’s really no "automatic" ways of managing this.



If the scheduler has the DREDs for each activity, when s/he sees which activities are on the CP with lots of DRAG, looking at the DREDs of each activity helps show where resources and funds might most profitably be targeted.



Fraternally in project management,



Steve the Bajan

R
Rodel Marasigan 👤 Member for 19 years 7 months

Lucas,

Task dependent use activity calendar and drive resource. Recommended setting is to used Fixed Duration and Unit or Fixed Duration and Unit/Time. Using this duration type ignore driving resources regardless Drive Activity dates by default is tick. This is the most commonly used activity type in planning with or without resources.



Resource dependent use resource calendar and recommended setting is to used Fixed Unit/Time or Fixed Unit. Resource dependent requires resource assigned and control activity behavior when Drive activity dates by default is selected.

S
Shah. HB 👤 Member for 17 years 6 months

Hi Hui



It depends on the nature of activity used in the project .There might be some activity where loading resources more could make the work get it done.Eg.Fixing Pipe in a room



Other depends on duration regardless of the resource the activity used Eg.Curing of structures

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts