Modifications in the updated Program from Base plan
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Shaji
In the existing baseline [ without updates ],you can revise the network logic where you find the issues and than update it with actual site scenario and check the status.
Dear Shaji,
Of course it is the right thing to do. It depends on the size of your project and the complexity of it. If you have a Contract and you submitted a Program of Works and the Engineer didnt return with comments, then this is the Schedule that you (Contractor) will be following to complete the project.
I assume that you are using FIDIC, and following article (8/3) once you realize that the actual progress at site does not represent the Program of Works, you need to modify your Program of Works to represent the actual (new information), making sure that you abide by the Conditions of Contract (scope, time).
With kind regards,
Samer