Calling all M&E Planners
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi,
My 2 pence worth of advise for M&E Planning...
First thing to note is you are at the mercy of the Main contractor regarding overall M&E duration! Increasingly, a good number of planners & PMs are taking into cognizance the fact that M&E package is probably the most integral part of a construction project, hence involving M&E from the onset.
Generally, I conside M&E to have 3 fixes - 1st, 2nd & Final. 1st Fix Electrical being your primary & secondary containment, conduit drops etc. 2nd Fix being cabling & termination & final fix - light fittings, sockets, spurs etc etc.
Also worth noting is the high level of co-ordination with other fit out trades such as 1st & 2nd side partitioning, painting & mist coating, ceilings etc etc.
As much as possible, I would avoid having 2 disciplines on 1 line of programme - e.g. M&E 1st Fiix - For the simple reason - That line of programme becomes as ambiguous as possible. Clear case of how long is a piece of string!
Hope this helps...
Kayode.
Hi all
I need help as I'm just getting my foot into M&E Planning...... Tell me what are basic things I have to consider when Creating the WBS from scratch in P6....... Just some notes on M&E would do....
cheers
Geoff
Dear Justin,
You can search the previous threads in PP, plenty of information is available. Enjoy the reading.
With kind regards,
Samer
Advice off anyone would be nice, not just M&E planners, but if there are any on here, please share your knowledge.
Mike Testro, you seem to be a seasoned professional from what I have read on here so far, any input greatly appreciated.