To all planners
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Dear Rola,
You might want to read the following as well:
" RESPONSIBILITY AND REQUIRED SKILLS FOR A PROJECT
PLANNING AND SCHEDULING PROFESSIONAL"
www.aacei.org/technical/rps/14R-90.pdf
With kind regards,
Samer
Greetings Rola
I think the experience it is your problem and the best to study and understand Drawings, Spec. and BOQ and discussing the coordination of these documents with experieced engineer for the method of executing of such activities
Regards,
Dear Rula,
There are good articles on the net about what makes a good schedule.
www.warnercon.com
With kind regards,
Samer
Dear Rola,
Please take it one step at a time. The Program of Works is built from Activities. You need to compare it to doing something that you can do very well, and have the same confidence.
An engineer with 1 year experience is a junior engineer on a project, whereas an Engineer with 40 years experience might be needed to build a skyscraper. The material used for both is concrete and steel.
To evaluate your program, you need to compare it to the actual progress at site. A good advice is to site with your construction crews and learn how they will proceed with completing their jobs. This is the challenge. It is like translating from Construction Language to Programing Language.
You always need to keep updating your work. Learn what the construction team has done on the 1st floor and model it in the remaining floors.
Can you answer the planning and scheduling questions that the Project Manager is asking from you. For example:
1. What are we going to complete next months and how many people do we need to complete it?
2. Did we complete all the submittals on time?
3. When is the material going to arrive at site?
4. How much invoicing have we done? How much scope did we complete?
5. What is the effect of the variation orders on the project completion date?
The more you ask, the more you learn. Good luck,
With kind regards,
Samer
Hi Rola
To be brutal - you are out of your depth and should not be planning work that you cannot construct yourself.
It does not matter what software you are using - if you cant build it you cant plan it - and MEP is one of the trickiest disciplines of them all.
Ask someone who does know how it all fits together and than SCHEDULE the plan that is described to you.
Do not forget the cinstruction interfaces with other trades.
Also whatever time is left for comissioning - it is never enough.
Best regards
Mike Testro
Hi Rola
Check out this link ,you could learn basics of MEP programme structure
http://planningplanet.com/forum/forum_post.asp?fid=1&Cat=1&Top=67703