about Resource Usage/Assigments Table

M
Mike Testro 👤 Member for 20 years 5 months

Hi Rafael



And a Merry Christmas to you and yours.



I am the cook in our house and on Christmas day I am cooking a whole small pig for 5 of us.



I have never cooked one before so it will be interesting.



Best regards



Mike Testro

R
Rafael Davila 👤 Member for 22 years 3 months

Mike,



"in PowerProject it is possible to assign different resources to different periods along the task" - I like this, P3 and SureTrak provides for this with a resource lag and resource duration. I don’t know how all this works out with the resource allocation algorithm but I would have a priority on the resource allocation algorithm and might be willing to split the activity in the few occasions this will happen in my jobs. If it does not affects the resource leveling algorithm then it can be handy.



I am also concerned about period postings a functionality not available in SureTrak, available in P3 only for actual period performance but you cannot edit it easily. As far as I remember within P3 you could edit your last period by running again post period performance without advancing to a new period and even enter negative values after making sure the cursor is inside the box.



I believe newer software versions provide better functionality to deal with period performance, planned and actual, this might include Asta PowerProject, Spider Project, P6 and MS Project.



Thanks for your reply and by the way have a Merry Christmas you and your family.



Best regards,

Rafael

M
Mike Testro 👤 Member for 20 years 5 months

Hi Rafael



The allocation of resources to tasks can have strange results - particularly if there are multiple calendars to consider.



In PowerProject the resource calendars over ride the task calendars but there is a toggle in the resource set up to "use task calendar" which helps a bit.



Also in PowerProject it is possible to assign different resources to different periods along the task - but you cannot link resources under the task logic - maybe this should be an add on.



Also you cannot assign resources outside the duration of the task.



When resheduling the task logic the resources follow the task.



Regarding updates a 10% time completion on the task will take out 10% of the resource allocation.



You cannot apply progress independantly to resources under one task.



I solve the resource problem by using tasks that carry only one resource by using bottom up FS links.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts