P6.2 - Change/Scope Control Methodology
Forum Sponsor
Top Posters
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Steve
Youll have to agree with management or customer when to draw a new baseline - and compare with the new one. As a BL is a complete copy of your project maybe 1000 BL would overcharge SQL Server.
There are different solutions: Always keep the original BL or work with a new one after each major change of scope.
For the print-outs we use Excel, but the data is from P6.
Regards
Dieter
Hi Steve,
Sorry to say that I cant provide clarification with regards to the use of templates as Im not practicing it. As they say, each and every project is unique. Some construction activities might be generic in terms but I believe there will always be difference in some applications or factors corresponding to a certain project.
As Dieter said, you need to establish a baseline for each and every changes that you make, meaning if you got a thousand changes, correspondingly, you got a thousand baseline in order to track your changes (with due respect to Dieter, I supposed thats what he meant, or am I wrong?).
cheers!
Thank you for your comments.
Do I adjust the budgeted costs (i.e. reduce to $O) resources, and essentially all activities which have been removed from scope. If so, how will I be able to use original budgeted information to plot curves if it has changed (and thus the original budget will not be visible within Primavera at a glance.
For activities added: Once added to the schedule, do I populate the original budgeted units/cost fields for all resources required for the new activity OR do I populate only the remaining units/cost fields (i.e. forecast)
OR do new fields exist (i.e. rev cost) that could be used to capture the cost impact of the scope changes while always showing the original budget.
Hopefully the above makes some sense. The real issue: where specifically should I show a reduction/increase in costs/units for removal/additions to scope within the schedule - while showing the original budget.
Anoon: Can you provide clarification on the use of templates - I am unfamiliar with this
Thanks
Steve,
May I add to what Dieter had advised. As you had mentioned resource loaded bottom-up scheduling, and change/scope control methodology, I believe this will always happen if you will use templates to develop a higher level (i.e. level 3 or 4) schedule during the early stage of the project (sorry Mike). For me, details or specifics - make the schedule. And changes to the scope will always impact your budget.
cheers!
Steve
I assume that your plan was signed and approved.
First youll have to create a baseline - as well after each change of scope. Be aware P6 only recognizes an activity if it still does exist in your current plan, so dont delete activities after your baseline was taken. Those activities you can set to duration, units, and costs = zero; maybe with a comment "due to scope change as of...". For my opinion this is better than just to delete activities.
Hope my assumption was right.
Regards
Dieter