LNG Pipeline Pre-commissioning Schedule required!

B
Ben Hall 👤 Member for 17 years 8 months
I
Izam Zakaria 👤 Member for 20 years



Get the contracts first from client. Go through everything on contract and get milestone dates (normally it would stated on contract)



Further study on barge availability (vessel that bring the numbers of pipe line)



Further study on weather contigency (during laying and installation of pipe line)



normally the pipe line will be assembled at onshore (refer to project execution )before they proceed installtion at deep sea



get productivity of welding joint (especially dive welder)



Bear in your mind they will proceed hydrotest (work pack) at onshore. get it from your company KPI.



U mean u need to complete the schedule which the activities is up to 1000? actually it’s a common practice by planners.(put engineering and procurement activities such like material, PFD, P&ID, specification, delivery, ex-works blablabla....





Last but not least...get liaise with your project management team ...come out the schedule first and let them comments....




Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts