Statistical data

L
Luca Masina 👤 Member for 17 years 4 months
S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Friends,



The Fabrication process time depends on the item being fabricated.



Structural Steel is usually divided into four sections;

Light steel

Medium steel

Heavy steel

Extra Heavy steel



The manhours spent in production (complete item) usually depends on the weight of the item in case it is just structural steel.



The range can be from 9hours/MT - 100+hours/MT depending on the type of structure and the availability of required equipment.



Best Regards,



SAmer

H
Hady Mohamed 👤 Member for 20 years 4 months

Luca,



Whilst allocating the durations for the welding activities, do not forget to allocate enough time for the "Fit-Up" phase the precedes the actual welding. That is, the edge preparation of both sides of the butt-weld, a tack weld in place, and an inspection by the QC Inspector of the quality of the Fit-Up process.



From my (limited) experience, the duration of the Fit-Up process can be overlooked and this may lead to inaccurate schedules.

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Luca,



Did you check the American Welding Society?



Or you can check the major welding companies like Lincoln and Esab. I am sure that they will have everything you want. It is a small call to your local supplier of welding materials. Definitely the manuals exist for a long time.



Best Regards,



Samer

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts