Resource Original Lag

A
Ahmed Elkordy 👤 Member for 17 years 6 months

i love you man

it worked

and i don’t even have to do it before i add the activity :] YOU ARE A LIFE SAVER!

A
Ali Farhat 👤 Member for 17 years 7 months

Hey Ahmad, I think I figured it out

Go to the project details, Resource Tab, uncheck the "Drive activity details by default" BEFORE you add the activity.

Add the activity, change the duration (45) then add the resource twice. The first resource: OD = 1 Lag = 1, the second resoruce OD = 1, lag = 75. I think this will work.

waiting ur response ;)

A
Ahmed Elkordy 👤 Member for 17 years 6 months

it changes directly not after scheduling.

here’s the thing the activity duration is 45 days so i set the resource duration to 1 or 0 days i don’t remember and set the lag to 75 days (it’s supposed to happen 1 month after the activity has finished), and what happens is the activity finish date is delayed by one month...on the spot, no scheduling.

you say it went well with you??

A
Ali Farhat 👤 Member for 17 years 7 months

Hey Ahmed, you recognize the delay in finish date when you are updating the schedule? or during planning. and does it change directly or after scheduling

A
Ali Farhat 👤 Member for 17 years 7 months

hehehehe...you beat me

i ran a similar scenario yesterday and it worked. i will work on it later and try to find an answer.

regards,

A
Ahmed Elkordy 👤 Member for 17 years 6 months

It is task dependent and the duration is fixed, i still don’t know where the problem is.

Thanks

A
Ali Farhat 👤 Member for 17 years 7 months

Ahmed, make sure the activity type is task dependent and not resource dependent, and duration is fixed.

A
Ahmed Elkordy 👤 Member for 17 years 6 months

Thank you all for your replies



Shahzad and Jose - I tried this method before in a previous project, it doesn’t appeal to me..it looks unprofessional, however, it seems like the only way.



Ali - Unfortunately no this doesn’t solve the problem, still the activity always seems to take the durations of the resources.



I’m still working on it, i know there must be a decent way of doing it.

Thanks again

A
Ali Farhat 👤 Member for 17 years 7 months

Hi Ahmad and all,

I hope this solves your problem,

First enable the project to add the same resource more than once to an activity: in the project details, resource tab

Second Make sure thar the resource in reference does not allow "Auto compute actuals": the resource window, details tab

Third Change the percent complete type of the activity to physical



Now add the resource twice to the activity,25% of your budgeted units for the first and 75% for the second

Set the resource original durations for both as 1 day

Set the resource original lag for the first as 0 and for the second resource as 30 days.

Check the distribution of resources in the resource assignment window..

I assume this would work.



Please note that you have to update manually the actual units of your resources.

J
José Reis 👤 Member for 17 years 6 months

Hi Ahmed Elkordy!



The Shahzad Sikandar wrote well, is a way to you to resolve your problem. Now I will like that make any question to you, maybe there is other way to resolve.



1º) Do you use other types of the cost like Nonlabor; Material or Expense?



2º)What "% Complete Type" you use to the tasks?



A hug!

S
Shahzad Sikandar 👤 Member for 20 years 4 months

what you can do is add another 1 day activity, give that a one month lag and assigned 75% of the cost or resource to that activity.



i hope this is ok.



if not please correct me.



thanks

shahzad

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts