Total float calculation in P5

I
Iftikhar Awan P.Eng. 👤 Member for 20 years

Here is the answer that I got from US Army Corps of Engineers website (publication# EP 415-1-5 (link is provided below):



"In the Precedence diagramming system, if start to start or finish to finish lags are used, it is possible for the total float on the start and finish of an activity to differ. In such an instance the start float may be more critical (smaller) than the finish float or vice versa."



www.usace.army.mil/usace-docs/eng-pamphlets/ep415-1-4/c-3.pdf



There is an example network schedule provided that explains the above.



Happy reading!

I
Iftikhar Awan P.Eng. 👤 Member for 20 years

This statement seems to be applicable to a group of activities under a summary group, because Primavera does show total float value for a summary group. I am not sure however if the P5 setting is applicable to summary groups only or to individual activities also.



I am doing a literature review at this time because I do remember seeing the terms ’start float’ and ’finish float’ somewhere.

A
A D 👤 Member for 19 years

Even I thought they are same, but check this out from p6 help menu:



If you base float on start dates, and all activities are assigned to the same calendar, total float is the difference between the earliest late start and the earliest early start dates in workperiods. For finish dates, the Project Management module uses the latest late finish and the latest early finish dates to calculate total float. The most critical float is the lowest total float encountered in the detailed activities from each summary group.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts