Schedule not using a Current Data Date

M
Mike Testro 👤 Member for 20 years 5 months

Hi Ken



You beat me to it - I was going to suggest that method.



I set lead in procurement to ALAP as a standard so that progress on the works reflects in the Lead In Activities.



Best regards



Mike Testro

K
Ken Barrett 👤 Member for 19 years

After much trial and error, I figured out that to make all activities that are not maditory starts as "start as late as possible" then sechdule... works like a charm...

C
Carmen Arape 👤 Member for 21 years 11 months

Ken,



Do not worry. It made sense ….



I have done that but at the beginning of a project where everything is going to happen therefore start date=data date. What if runnings were simulated using constraint dates. Name it: start ON, or mandatory start and so on.



Your case is different, You have a portion in your schedule which is actual, real execution that you do not want to mess up. BUT you want to run the What IF scenarios. First of all, I would recommend making a copy of the original schedule and work with the copy.



If I were you I would create key points in the schedule (milestones) where I can link the activities being affected to this milestone. The key point would be taken the place of Data date with a constraint date. These points will be linked to activities being executed. Minimize links of these key points with activities under execution.



Ken , I hope my answer makes sense to you

Cheers,




Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts