mep sequence in building

J
Johnny Wee 👤 Member for 18 years 11 months
S
Samer Zawaydeh 👤 Member for 17 years 11 months

Dear Johnney,



It depends on the size of project that you have. Either go by



1st fix electrical: Walls, ceiling and Floor

2nd fix electrical: pulling cables and wires,

3rd fix electrical: sockets, cover plates, lighting fixtures and commissioning.



1st fix Mechanical

2nd fix Mechanical

3rd fix Mechanical: installing fixtures, pads and commissioning,



for big size project, it is preferred that you go by system. For MEP, it can run between 15-25 systems.



Let me know if you have a more specific question.



Best,



Samer

Forum Sponsor

Top Posters

J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts