mep sequence in building

J
Johnny Wee 👤 Member for 18 years 10 months
S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Johnney,



It depends on the size of project that you have. Either go by



1st fix electrical: Walls, ceiling and Floor

2nd fix electrical: pulling cables and wires,

3rd fix electrical: sockets, cover plates, lighting fixtures and commissioning.



1st fix Mechanical

2nd fix Mechanical

3rd fix Mechanical: installing fixtures, pads and commissioning,



for big size project, it is preferred that you go by system. For MEP, it can run between 15-25 systems.



Let me know if you have a more specific question.



Best,



Samer

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts