mep sequence in building
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Dear Johnney,
It depends on the size of project that you have. Either go by
1st fix electrical: Walls, ceiling and Floor
2nd fix electrical: pulling cables and wires,
3rd fix electrical: sockets, cover plates, lighting fixtures and commissioning.
1st fix Mechanical
2nd fix Mechanical
3rd fix Mechanical: installing fixtures, pads and commissioning,
for big size project, it is preferred that you go by system. For MEP, it can run between 15-25 systems.
Let me know if you have a more specific question.
Best,
Samer