mep sequence in building
Forum Sponsor
Top Posters
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Dear Johnney,
It depends on the size of project that you have. Either go by
1st fix electrical: Walls, ceiling and Floor
2nd fix electrical: pulling cables and wires,
3rd fix electrical: sockets, cover plates, lighting fixtures and commissioning.
1st fix Mechanical
2nd fix Mechanical
3rd fix Mechanical: installing fixtures, pads and commissioning,
for big size project, it is preferred that you go by system. For MEP, it can run between 15-25 systems.
Let me know if you have a more specific question.
Best,
Samer