Interruptible vs. contiguous

S
Samer Zawaydeh 👤 Member for 17 years 11 months

Hi,



Your activities should be connected to the resources. So if you have material deliveries coming in with certain frequency and the rate of completion at site is higher than the rate of supply to site you will have interrupted duration; that is once the material comes to site you can complete the activity.



Again, if you have a special person doing a certain job like commissioning of a system, then when this person at site, this activity can be ongoing.



On the other hand, excavation, concreting, steel reinforcement, block building, plastering, and most of the civil works are continuous activities.



Good luck,



Samer

A
Anoon Iimos 👤 Member for 19 years 9 months

i guess it’s like progress override or retained logic



(i’m just a trying hard aspiring planner by the way)

Forum Sponsor

Top Posters

J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts