Interruptible vs. contiguous
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi,
Your activities should be connected to the resources. So if you have material deliveries coming in with certain frequency and the rate of completion at site is higher than the rate of supply to site you will have interrupted duration; that is once the material comes to site you can complete the activity.
Again, if you have a special person doing a certain job like commissioning of a system, then when this person at site, this activity can be ongoing.
On the other hand, excavation, concreting, steel reinforcement, block building, plastering, and most of the civil works are continuous activities.
Good luck,
Samer
i guess its like progress override or retained logic
(im just a trying hard aspiring planner by the way)