No Subject Specified
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
yest thats right
call them Pour 1, pour 2 and so on,
code them if you want to see them in different areas but under one header i-e Concrete Pour (once all pour activities are coded against activity code (concrete pour)
you could also do resource linking or concrete supply linking.
hope this helps
cheers
hi anoon,
thanks for the information youve given.
regards,
bon
there is no problem if you repeat the same activities a thousand times, in construction, it is the only way, i suggest you use activity codes (more flexible)
For example:
1.layout
2.formworks
3.rebars
4.quality inspection
5.place/pour concrete
6.strip formworks
you can repeat the same group of activities (above)for all the concrete structures that you may have.
once you have established your codings, then its easy to apply filters, so that you will only show "pour concrete" to occur on certain dates.
hth
hi mr. charlie,
thanks for your help. i will do it.
regards,
bon
Bon,
You need to establish WBS at sufficient level to place common activity pour concrete.
Please review the idea behind WBS
Regards,
Charlie