On the menu bar got to, Enterprise, Resources.
There is a tab at the bottom of the screen called Units & Prices.
On this you can add a new rate (price/unit) and give an effective date for each resource.
Oliver,
I am using Primavera P6. This schedule was built by the contractor and they used both labour cost and material cost to generate the budget. That particular planner has moved on so my project manager is asking me the best way forward?
Don,
It depends what software you are using? (If you are talking about changing the rate in the plan)
Qui Wei,
In this case the scope has not changed it is just rate increase.
To Don Gilchrist:
I think should got 2 ways to consider this kind of situation, and the increasement of budget is due to work scope (task) change or the material fees , you need to consider that first.