Engineering Submittals!

A
Anoon Iimos 👤 Member for 19 years 8 months

Engineering Submittals? or is it Detailed Design Deliverables?



I suggest you set the budget in terms of man-hours (total).



If you had consumed half of your man-hours and you think that what you got actually (deliverables) is not workable, change your consultant.


R
Rami Al Haddad 👤 Member for 20 years 11 months

Thank you guys for all your replies,



let’s take this discussion further, u all agree on that 2 activities are enough; say submit and review, which makes perfect sense.



but updating is a different issue cuz:



Chances are the submittal will not be approved from the first time, during schedule preparation i take this into consideration by making sure submit/review activities are start well in advance of the time they are required (normally 2 to 3 submit/review cycles). now once thats established, the updating is a different story.



the % complete method: the % is not accurate since u never know how many re-submittals ur going to do! simply considering it 50% until it is approved doesn’t make much sense either! besides, a submittal is never a submittal until it is actually complete and approved.



lets not use a % complete! and put just actuals! what then! what if the submittal is rejected! u will remove the actuals on the next update! it doesn’t sound right either! as a matter of fact! it is confusing! one update its done! the next it’s not!



i don’t like the % complete way! in any case! it doesn’t really show whose delaying the submittal or what! it just shows 2 activities in progress! which is not the point! the point is! which activity is holding the progress! submittal or review!



so what do u think now guys! for me i’m still investigating!



thanks again for all the replies!

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Rami,



We are showing all the submittal in the "Program of Works" this is divided into 4 sections; Architectural, Civil, Mechanical, Electrical. All materials in the BOQ to be included.



Percentage is used to show progress on the submittal. 100% is given when the material is "Approved".



Best,



Samer

E
exofo Ng 👤 Member for 17 years 10 months

To me, engineeering consists of several steps (Preliminary, discussion, sent for approval, return of approval, modification etc) if this step could be broken down in % and measured against Mhr expediate. it would at least provide a minmium platform for measuring progress, But again, it depend on the skill level of the designer..

J
James Shimmon 👤 Member for 19 years 4 months

quite right Dieter, engineering are notoriously slippery and need to be pinned down so you can hold them accountable

D
Dieter Wambach 👤 Member for 19 years 4 months

Rami

I would prefer 2 activities as well. Between issue/submission and approval date weeks easily pass. Later you’ll be able to show who is responsible for a delay.

In addition, these dates can influence percent complete and the cash flow.

Regards

Dieter

J
James Shimmon 👤 Member for 19 years 4 months

if you are showing it as two discrete activities in the schedule then I would use method 2, you could then follow up with adding another activity that involves rework from the engineering review

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts