Total Float Calculation in P6 for Multiple Projects
Forum Sponsor
Top Posters
James Williams
75 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Oh, Paul Harris,
Its great to hear from you. I solved the problem according to your first option. The second option is interesting, I will try this one too.
Thanks Paul,
Best Regards,
Shahab
This is one of the many problems with P6 when one is trying to use it on more complex projects as it does not have a subproject function as found in P3.
The two options I have used are:
1. Set the Project Must Finish Dates for both projects to be the same, or
2. Establish milestones in each subproject that are linked to the latest subproject finish date.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
Shabab
By design activities with a mandatory constraint have a total float=0. Exception if your data date is later than the constraint date.
Regards
Dieter