There is no standard process but you need to identify potential risk that will delay your programme completion date or major key dates for example: Lack of Design, too many design changes, late procurement, budget contraints, delivery of long lead items, unknown ground conditions, etc. The important thing is to identify them early and raising the issues to the management so that they can be mitigated.
Cheers,
Daniel