Schedule Risk Analysis.

D
Daniel Limson 👤 Member for 24 years 7 months

There is no standard process but you need to identify potential risk that will delay your programme completion date or major key dates for example: Lack of Design, too many design changes, late procurement, budget contraints, delivery of long lead items, unknown ground conditions, etc. The important thing is to identify them early and raising the issues to the management so that they can be mitigated.



Cheers,

Daniel

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts