Procurement period of pipes
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
I have been trying to get CS tube and the lead time varies from country to country.
Sometimes the client insists that tube or pipe has to be of european or Nth American origin which can be a lead time of 35 weeks (especially if its seamless & not welded). Whilst I have been getting better lead times from China and Estonia.
Our procurement dept are now trying every corner of the globe.
It depends upon your supplier exclusively. His factory profuction capacity, stock at that period and projects in his hand.
So, its better to call ur vendor rather than asking from planners.
Call your vendors for more accurate answer. Dont rely on planners, because planners do also ask suppliers for this kind of information.
My poject is using CS pipes 20" dia. or more, and fittings previosuly estimate 33 wks of lead in time but the vendour is quite quick getting it ready in 20 wks.