Tender Planning workload per year, per Planner ??

T
Tom Howard 👤 Member for 22 years 11 months
G
Glenn Douglas 👤 Member for 20 years 1 month

johny,



Those descriptions are going up on the managers office wall.

(I could do with a new job).



Glenn

A
Andrew Pearce 👤 Member for 24 years 11 months

Buna Dimineata, Good morning,

I think the original question asked was how many project bids a construction planner could handle at tender stage in any one year. (I presume we are talking building construction projects Hotels, Offices, Hospitals and the like)



I suggest that this is not an easy question to answer as any bid may have different submission requirements. It also depends on what service you expect the planner to provide, obtain Tower Crane, scaffolding quotes etc. Produce programme method statements, phasing plans etc.



Unless the project is extremely large and/or complex I would expect a proficient planner to manage at least 2 tenders per month.


J
James Barnes 👤 Member for 18 years 9 months

Tom,



if your firm thinks that maintaining site schedules is a job to be tacked onto the tasks of the tendering planner, then I think you have all the answers you need about how seriously they take their planning and how unlikely it is that they’d listen to anyone telling them that they’re not putting requisite resources into the discipline.



at the rate you’re talking, you would be planning literally billions of euros / pounds worth of tenders a year.



This is not planning, it can’t be. It’s pretty pictures to procure projects.



There is a shortage of planners in Europe at the moment, you don’t need to be some BDMs whipping boy ... unless you get a kick out of it, that is ;-)

T
Tom Howard 👤 Member for 22 years 11 months

Many thanks for all the informative replies (and the auto email notifications that generated with each one).



Can I retract my previous statement and open the question up to South African diamond planners as well please ???

J
Johny Kesserwany 👤 Member for 18 years 8 months

Hi Tom,



I don’t have European work load average for planners.... But read the followings may be it would help!!!



CONSTRUCTION TERMINOLOGY - Where do you FIT ???



Project Manager : is a Person who thinks nine women can deliver a baby in one month



Construction Manager : is one who thinks a single woman can deliver nine babies in one month



Contract manager : is one who asks if the baby is in the budget ( and if it saves money to adopt )



Project Engineer : is a person who thinks he can deliver a baby if no man and woman are available.



Section Engineer : is a Person who thinks it will take 18 months to deliver a baby



Design Engineers : are still figuring out how to produce a baby



Procurement Team : thinks they don’t need a man or woman; they’ll produce a child with zero resources



Document Control Team : thinks they don’t care whether the child is delivered they’ll just document 9 months.



Quality Auditor : is the person who is never happy with the PROCESS to produce a baby.



Site Engineers : don’t care...they just want the woman!!!



Client : is the one who doesn’t know why he wants a baby.

Business Development Manager : is the one who is trying to make the baby with the client’s wife.



QUANTITY SURVEYOR : is the one who wait for the baby to be delivered, so that they can make claim to be its Father.



Last but not Least



Planning Engineer : is the one who is working around the clock for nine months to prove that the baby is not a bastard!.



Regards

JK

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts