Planning to avoid Critical Mass

J
James Griffiths 👤 Member for 20 years

James,



Where you have independent activities, then the flexibility that exists is only dependent upon the number of different orders-of-execution. ie. if you have three activities,A,B,C, then there are 6 different orders-of-execution.



The only way to acquire more efficient orders-of-execution is by planning each activity at a deeper-and-deeper level of detail. This will then raise any resource conflicts, thus defining the shortest critical path. Essentially, you’ll be "line-balancing", such that no activity will have any float. This is how manufacturing companies make themselves more efficient - by removing "dead time" wherever possible.



I don’t know of any particular texts that deal with this sort of thing, but good scheduling software should enable you to get a pretty good answer. If your resources are finite, then that makes life a lot easier. Once again, however, you will need to programme at a very deep level of detail.



We had a good example of such an exercise; whereby there was a dynamic handling system that went through a specific series of activities, with various paths that crossed. The objective was to determine the maximum number of systems that could be used before a process "clash" ocurred. We programmed the activities down to the last second. It transpired that we could only run two sets of handling elements concurrently. If we used a third, then a clash would occur after a set time. Ok, only using two sets of elements gave us a "less efficient" process, but the advantage was that you didn’t have to spend the capital cost and also didn’t have to worry about a clash.



HTH



James.


Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts