copying of same activities

I
Ian Dack 👤 Member for 18 years 1 month

Yes, your replies are the way out for you V, just remember to review when all are copied over then start to add your inter-relationships with each floor.

Review, review & review again.

good luck,

Ian

D
Dave Ellis 👤 Member for 15 years 6 months

Hi

 

You could create a WBS branch for a floor & just copy that.

M
Mangesh Khuspe 👤 Member for 19 years 1 month

hi dear

look what i do is create activities for 1 floor, then from this bunch, i create 2 floors, then copy this bunch of activities for two floors and paste them and now link this bunch with earlier one thus creating activities for 4 floors, now this 4 floors will create activities for 8 floors. in this way u can create prog for no of storeys in very less time. (but the building must be identical).



regards

mangesh

V
Vijayendra Surve 👤 Member for 19 years 1 month

thank you sir,

i was trying in global change if optionis there but then sir this process is taking whole lot of time...so bit labourious...anyways ways thks once again..

M
Mangesh Khuspe 👤 Member for 19 years 1 month

hi

considering the building is identical, first u can create all detailed activities for 1 floor, link them, schedule it.

then select all and paste them and now link them with earlir ones. now copy this bunch and paste it again and continue this process, until u ahve finished.(thats the way i do).

secondly there is no option other than using fragnets.

so u will have to proceed with it.



regards

mangesh

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts