Madatory Constraint
Forum Sponsor
Top Posters
Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Hi gracia,
Mandatory Start and Finish constraints completely override network logic and do not allow for float calculations. Suggest that your contractor should have used START ON or START NO EARLIER THAN or START NO LATER THEN constraints.
NOTE: Mandatory Start and Finish constraints do not obey CPM rules. The activity configured in this manner will be scheduled to start on the date given even if all predecessors are not complete. START ON constraints work the same as a MANDATORY START but also obey CPM logic rules.
START NO EARLIER THAN allows for float calculation in delay direction and START NO LATER THAN allows for float calculation in the accelerate direction.
So, yes of course, program submitted is technically and legally correct.
Cheers,
Raviraj A Bhedase
I need to refesh my point, the contractor has submitted the schedule without mandatory date constraint in the start date and finished date,
Is this type of schedule valid? Legally or Technically!!
Mandatory or Early Constraint
Date Constraints
Bernard Ertl
InterPlan Systems