MEP Installation Sequence

S
Shaiju Thomas 👤 Member for 20 years 2 months

Thanks Andrew, I agree. We have to look into the combined services drawings, sections. But it is difficult to show this things while developing a program.

A
Andrew Pearce 👤 Member for 25 years

Generally there is not a typical sequence because all installations are different. You need to look at the drawings, particularly any sections. Think what is highest, install that first, think what is most flexible, install taht last.

You may find that in most cases Duct and any form of pipework is installed prior to electrical works.