rundown curve
Forum Sponsor
Top Posters
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
Thanks a lot Rollen;
Could u please guide me to find material or exemples?
Best regards.
Hi Marcio,
Run-down curves are best applied in items that require follow up to get the value to zero in order to complete the project.
This looks differently in the normal S-curve as this has an initial value >0 and finally completes on 0.
One example is that, approval of engineering drawings from the client/consultant which will affect the delay once a timely rundown does not take place.The more higher figure we have for the unapprove drawings, the more we see that our project is concern of delay.
Same thing applies to the Procurement Packages that has been defined in the original plan. Total Procurement packages should run down to 0 before some construction activity start.
So our curve will look like a descent hill which our project tracking starts at the top.
Cheers,
Rollen
Could u please guide me to find meterials about this topic?
Best regards.