MEP

P
Pacifico Pallasigui 👤 Member for 22 years 4 months

Thanks for all the help & tips bro



The project is a two building one is 7 storey bldg and adjacent to that is a 9-storey building and this two buildings is divided by an atrium.



Thanks

pacifico

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

dear Sir,



a.TESTING & COMMISSIONING is rquired for all the system listed above i.e u have to connect all the systems above with an activity name "TESTING & COMMISSIONING" at the end.

b. Depends on the built up area of the building , nos of flooors how much resources u have and all .

c. It can start after the set up for the system has been completed personally i prefer this activity at the end of completion of the set up.

d. Power distribution is needed for all the listed systems.

for a copy of my project u can mail me [email protected]

i may be late to reply as will move out on vacation

regards

deb

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts