MEP
Forum Sponsor
Top Posters
S Z
4 posts
Iftikhar Awan P.Eng.
19 posts
ahmad rashidi
4 posts
paulciszewski
0 posts
Catalin Suditu
11 posts
Laraib Fatima
0 posts
Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts
Abkar Bannayan
25 posts
Thanks for all the help & tips bro
The project is a two building one is 7 storey bldg and adjacent to that is a 9-storey building and this two buildings is divided by an atrium.
Thanks
pacifico
dear Sir,
a.TESTING & COMMISSIONING is rquired for all the system listed above i.e u have to connect all the systems above with an activity name "TESTING & COMMISSIONING" at the end.
b. Depends on the built up area of the building , nos of flooors how much resources u have and all .
c. It can start after the set up for the system has been completed personally i prefer this activity at the end of completion of the set up.
d. Power distribution is needed for all the listed systems.
for a copy of my project u can mail me [email protected]
i may be late to reply as will move out on vacation
regards
deb