But that 5% of the engineering means a lot to the overall construction project, especially in the EPC or Fast-track project
Yes, its about right!
waaleikou assalam ( just to upset our christian friend;)
happy to see here, I hope your new work rocks !
friendly
mimoune
Assalamou aleikoum
In general we get those rate in petrochemical project :
Engineering 5-6 %
Procurement 50 %
Construction 44-45%
Commissioning 1%
Hi Kumar ,
In my opinion, complete engineering + erection + commissioning company.